: LG reviews progress of AIIMS, IIT, Jambu Zoo through camera-mounted drones #IndiaNEWS #State Excelsior Correspondent Jammu, Jan 30: Lieutenant Governor, Manoj Sinha on Sunday reviewed the progress
LG reviews progress of AIIMS, IIT, Jambu Zoo through camera-mounted drones #IndiaNEWS #State
Excelsior Correspondent
Jammu, Jan 30: Lieutenant Governor, Manoj Sinha on Sunday reviewed the progress of mega projects of Jammu Division through camera-mounted drones via videoconferencing from his office at Raj Bhawan.
The review included three undergoing projects- AIIMS Jammu, IIT Jammu, and Jambu Zoo. The Lieutenant Governor lauded the efforts of implementing agencies for fast progress on the projects.
During the meeting, the chair was briefed about the physical and financial progress of the projects.
Rs 1661 crores have been sanctioned for the AIIMS Jammu project at Vijaypur including Rs. 1452 cr for construction & Rs. 209 cr for Medical Equipment & Furniture, while works worth Rs 1253.78 Crores have been tendered so far, informed Prof. (Dr.) Shakti Gupta, Director, AIIMS Jammu.
Under Phase-I of the project, the prestigious project includes Hospital; Medical College; Nursing College; Staff Quarters; Student Accommodation; Auditorium, AYUSH building, Night Shelter and other development works.
It was informed that the manpower deployed at the site has been enhanced manifold for completion of the work within the stipulated time-period.
Briefing about the progress made on permanent Campus of IIT Jammu, Dr. Manoj Singh Gaur, Director IIT Jammu informed the meeting that an amount of Rs 1283.94 Crores have been sanctioned for the project.
It was informed that completed works under Phase-1A and Phase-1B have already been inaugurated by Honble Union Home Minister, while works under Phase 1C are in progress.
Giving details about the Jambu Zoo, Suresh Kr. Gupta, PCCF / Chief Wildlife Warden, J&K, briefed that funds amounted to Rs 49.17 crores have been approved under JKIDFC against the total project cost of Phase-I worth Rs 62.41 Crores.
Pertinently, Central Zoo Authority (CZA) was approached for approval of layout plan as required under the provisions of Central Act i.e Wildlife Protection Act, 1972 and revised layout and animal enclosure designs were submitted to CZA for approval.
Animal Enclosure Designs were approved by CZA on 27-08-2021. Master Layout Plan submitted to CZA on 12-08-2021 after incorporating the observations made by DIG CZA during her visit to Jambu, it was informed.
The expected dates of completion of the mega projects are March 2023 for phase 1 of AIIMS Jammu, September 2022 for phase 1 of Jambu Zoo, and April 2023 for phase 1C of IIT Jammu.
Dr. Raghav Langer, Divisional Commissioner Jammu, and concerned officers of executive agencies also attended the meeting.
The post LG reviews progress of AIIMS, IIT, Jambu Zoo through camera-mounted drones appeared first on Jammu Kashmir Latest News | Tourism | Breaking News J&K.
Intraday stocks under 50 NSE India Twitter of India
More posts by @IndiaNEWS
: S.Korean startup acquires Samsung SDS home IoT biz #IndiaNEWS #Business South Korean prop-tech startup Zigbang is acquiring Samsung SDS home internet of things (IoT) unit for an undisclosed sum.
: Epic to keep giving away free games in 2022 #IndiaNEWS #Gaming Fortnite developer Epic Games has confirmed that it will continue to give games away in 2022. Some of the games Epic has offered in
0 Comments
Sorted by latest first Latest Oldest Best
Terms of Use Create Support ticket Your support tickets Stock Market News! © desicheers.com2024 All Rights reserved.