: Odisha sanctions Rs 150 crore for Khurda-Bolangir line, 10.5 km new line commissioned #IndiaNEWS #Metro Bhubaneswar: With the Indian Railways commissioning the 10. 5 km of newly-laid broad gauge line
Odisha sanctions Rs 150 crore for Khurda-Bolangir line, 10.5 km new line commissioned #IndiaNEWS #Metro
Bhubaneswar: With the Indian Railways commissioning the 10. 5 km of newly-laid broad gauge line between Bichhupali and Jhartarbha of Khurda Road-Bolangir rail line project, the Odisha government has sanctioned Rs 150 crore for speedy execution of the much-awaited project.
Principal Secretary, Commerce and Transport Department, BP Sethi, has directed state government officials to release the fund to railways for early completion of the project.
The state government has given land free of cost and bearing 50 per cent construction cost for the 306. 25 km Khurda Road-Bolangir railway project.
I am directed to convey the sanction of the Governor to an expenditure of Rs 150 crore only for development of Khurda Road-Bolangir NBG Rail Link Project from 112 km–289 km during the year 2022-2023, Transport Department Financial Advisor cum Special Secretary wrote to the Accountant General.
Recently, the state government held a high-level meeting with senior officials from Central government, Railway, Forest Department and Revenue Department to expedite the project. Decisions have also been taken to fast-track the forest clearance at the earliest in a time bound manner, the official said.
Though survey of the new rail line between Khurda and Bolangir, connecting the coastal region of the state with the western district, was done in 1945, it got sanction from the Centre only in 1994-95 and the project is already delayed by more than 20 years due to lack of funds following which the state government signed an MoU with railways to contribute certain amount of funds for expediting the works.
Meanwhile, sources said the ambitious project is also being delayed due to non-issue of Stage-I forest clearance. Of the total length of 306 km of the Khurda Road-Bolangir new railway project, 91 km from Khurda Road to Nuagaon has been commissioned. Now, another 10. 5 km between Bichhupali and Jhartarbha is commissioned.
Officials said that the work is in progress from Nuagaon to Daspalla (91 km to 106 km) and target is set to commission it by March 2023. The work from Daspalla to Buguda (106 km to 121 km) is very slow due to non-issue of Stage-I forest clearance from the Ministry of Environment and Forest, the sources said.
Similarly, work from Buguda to Banigocghha is also yet to start due to non-issue of the Stage-I forest clearance. In total, the Government of India is yet to issue required forest clearance from 112 to 180 km while the work from 180 to 275 km is in progress and work at 275-301 km already commissioned.
Meanwhile, the East Coast Railways in a statement said that the Commissioner of Railway Safety (CRS) has inspected this newly laid Bichhupali and Jhartarbha line on November 10.
Intraday stocks under 50 NSE India Twitter of India
More posts by @IndiaNEWS
: Weekly horoscope November 14-20: Check predictions for Aries, Taurus, Gemini and other signs #IndiaNEWS #Feature Here is a guide to the week ahead for you. This is your forecast for November 14-20.
: Stokes, Curran win T20 World Cup for England, break Pakistani hearts #IndiaNEWS #Prime News Melbourne: Englands golden generation of white-ball cricketers overcame a spirited Pakistan to win the T20
0 Comments
Sorted by latest first Latest Oldest Best
Terms of Use Create Support ticket Your support tickets Stock Market News! © desicheers.com2024 All Rights reserved.